Preparations

  • Assess electrical and mechanical state
  • Procure engineering plan to relocate vessel
  • Drain fuel tank and refuel with fresh diesel
  • Recommission mechanics
  • Relocate vessel to suitable marina for commencement of works

Phase I

  • Develop ship Operating Manual; procure copies of original Kelvin documentation
  • Procure and import spare parts from around the world including complete replacement engines and gearboxes 
  • Relocate the vessel to allow access from land and commencement of urgent remedial activities
  • Lift the vessel out of water, clean hull and inspect condition 
  • Repair hull as required whilst boat is lifted
  • Undertake full survey for class 1E marine survey
  • Establish the Friends of MV Perth club

Phase 2

  • Establish governance and operating structure to allow the commencement of operations
  • Relocate MV Perth back to her home on the Swan River
  • Agree extent of restorative works with the Friends
  • Prepare outline budgets